Reported by MK.
Make a list of WP which can be seen in WP. In the best case, the Dasboard 1.0 and 2.0 to be associated with Planning tool.
A/C:
If committed to master it should be automatically deployed to kbss
Make a list of found issues in Bachelor thesis here. Each item should be either new issue or just a text (if you are not sure it makes sense to implement). Note, that issues should be added to proper repository (react-maintenance-planner vs. csat-maintenance-planner)
A/C:
Add drag and drop feature for entire block of works. To drag it and move it to another set of days. Preferebly with all dependent work blocks.
There might be some issue like waiting for material or stoppage of works for various reasons and we want to be able to move entire work blocks to the future.
priority 1/5 = lowest
priority 5/5 = highest
No tasks beside closed ones should be in the project.
Currently it is this one:
M-ABOI/H-22 12Y
Recommended by MK.
When task is selected, it should display:
set it by default - now when i load new WP, the zoom is not always set to show all the days but just some
Cannot see how easily add or remove tasks.
Reported by MK.
CSAT would like to have workplan based on historical data built and visualized. However, when WP would start, workplan should be amended with actual data exported from AMOS, available now on FTP.
Example: TASK 291000-20-1-600 planned on Friday 1.1.2021. Actually performed on Monday the forth. The blue "rectangle" would be erased
set start/end/duration of the task by setting exact date/time and not only by moving it with coursor.
in excel there is clearly see day and night shifts along with the dates.
Adding El. power ON/OFF and JACKS ON/OFF on progress bar
Once API is finished, interface of work package should be written to avoid "any" type
Resources and tasks should be able to create and remove directly from tree
I cannot see which WO i have chosen, hence is shown in the app.
When you click on WP, it should show same content as planning component:
https://react-maintenance-planner.netlify.app/
Some work orders do not have any start or end therefore, they are not displayed on the plan-editor. There should be a mean to keep track of these work orders.
-Possible implementaion:
It should show same information as in task cards (green boxes)
Might be helpful along with dates to add counter of days - Day 1, Day 2 etc. to show for each WP.
@blcham:
In order to visualize different days, we need to differentiate night/day shifts.
Confirmed by @kalamartin:
@blcham For clarity I think it would make sense to rename the projects:
Reported by MK.
A declarative, efficient, and flexible JavaScript library for building user interfaces.
🖖 Vue.js is a progressive, incrementally-adoptable JavaScript framework for building UI on the web.
TypeScript is a superset of JavaScript that compiles to clean JavaScript output.
An Open Source Machine Learning Framework for Everyone
The Web framework for perfectionists with deadlines.
A PHP framework for web artisans
Bring data to life with SVG, Canvas and HTML. 📊📈🎉
JavaScript (JS) is a lightweight interpreted programming language with first-class functions.
Some thing interesting about web. New door for the world.
A server is a program made to process requests and deliver data to clients.
Machine learning is a way of modeling and interpreting data that allows a piece of software to respond intelligently.
Some thing interesting about visualization, use data art
Some thing interesting about game, make everyone happy.
We are working to build community through open source technology. NB: members must have two-factor auth.
Open source projects and samples from Microsoft.
Google ❤️ Open Source for everyone.
Alibaba Open Source for everyone
Data-Driven Documents codes.
China tencent open source team.