singleserver_markovianmodel's Introduction

EX NO:07

DATE:15.6.22

Single server infinite capacity - Markovian Model

Aim :

To find (a) average number of materials in the conveyor (b) suitable length of conveyor (c) waitinging time of the material in the conveyor, if arrival rate of material follows poisson process 5 per minuates and serivice rate of lathe machine follows exponential distribution with mean serice rate 6 per minutes.

Software required :

Visual components and Python

Theory:

Queuing are the most frequently encountered problems in everyday life. For example, queue at a cafeteria, library, bank, etc. Common to all of these cases are the arrivals of objects requiring service and the attendant delays when the service mechanism is busy. Waiting lines cannot be eliminated completely, but suitable techniques can be used to reduce the waiting time of an object in the system. A long waiting line may result in loss of customers to an organization. Waiting time can be reduced by providing additional service facilities, but it may result in an increase in the idle time of the service mechanism.

image

image

Procedure :

  1. Calcualte average number of materials to be waitted in the conveyor using given data.
  2. Create a empty project in visual component tool and add visual legacy component to the project.
  3. Drag a feeder and place in a place and choose the appropriate materal.
  4. Calculate conveyor length usng material size and average number of materials to be waitted in the conveyor
  5. Choose the two conveors from components, add one conveyor with feeder.
  6. Drag Lathe machne from machine library and place in the appropirate place.
  7. Drag machine trending inlet and outlet from visual legacy and add them to the two conyeors in the approprate manner.
  8. Drag robot manager and robot from visual legacy and place in between two conveyors.
  9. Connect all machine trending inlet, outlet, robot manager and lathe machine using interface menu.
  10. Run the program.

Experiment:

55

Program :

Developed by:
 Register Number:212220230036
 Name:PRASHETHAA R

56

Output :

57

Result:

The average number of materials in the system is 4 and the conveyor is 3.2, and average waiting time of each materials in the system is 60 seconds and conveyor is 48 seconds are calculated.

singleserver_markovianmodel's People

Recommend Projects

  • React photo React

    A declarative, efficient, and flexible JavaScript library for building user interfaces.

  • Vue.js photo Vue.js

    ๐Ÿ–– Vue.js is a progressive, incrementally-adoptable JavaScript framework for building UI on the web.

  • Typescript photo Typescript

    TypeScript is a superset of JavaScript that compiles to clean JavaScript output.

  • TensorFlow photo TensorFlow

    An Open Source Machine Learning Framework for Everyone

  • Django photo Django

    The Web framework for perfectionists with deadlines.

  • D3 photo D3

    Bring data to life with SVG, Canvas and HTML. ๐Ÿ“Š๐Ÿ“ˆ๐ŸŽ‰

Recommend Topics

  • javascript

    JavaScript (JS) is a lightweight interpreted programming language with first-class functions.

  • web

    Some thing interesting about web. New door for the world.

  • server

    A server is a program made to process requests and deliver data to clients.

  • Machine learning

    Machine learning is a way of modeling and interpreting data that allows a piece of software to respond intelligently.

  • Game

    Some thing interesting about game, make everyone happy.

Recommend Org

  • Facebook photo Facebook

    We are working to build community through open source technology. NB: members must have two-factor auth.

  • Microsoft photo Microsoft

    Open source projects and samples from Microsoft.

  • Google photo Google

    Google โค๏ธ Open Source for everyone.

  • D3 photo D3

    Data-Driven Documents codes.